At the end of week 10, this project has cost $9,000 and has an
Question # 00093865
Posted By:
Updated on: 08/18/2015 03:47 PM Due on: 09/17/2015

At the end of week 10, this project has cost $9,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars.
Duration (weeks) | ||||||
5 | 10 | 15 | 20 | 25 | % Comp | |
Conceptual Design | 10 | 6 | 100% | |||
Graphics Design | 12 | 6 | 4 | 30% | ||
Copyright | 4 | 5 | 6 | 0% | ||
Samples | 4 | 2 | 0% | |||
Tooling | 6 | 9 | 4 | 0% | ||
Production | 2 | 6 | 14 | 0% | ||
Total | 10 | 18 | 22 | 26 | 24 | |
Cumulative | 10 | 28 | 50 | 76 | 100 |
Select one:
a.2.1 b.1.5 c.1.8 d.2.5
-
Rating:
5/
Solution: At the end of week 10, this project has cost $9,000 and has an